Garden City Safe Routes to Schools

Project Description:
This project consists of constructing drainage improvements, curb and gutter, and an eight foot wide shared-use bicycle and pedestrian asphalt trail on the east side of Garden City Boulevard beginning at Yellow Mountain Road to the terminus of the project at Davenport/Ivywood Street.   
 
 

Project Construction Start:

 
August 2015

Target Completion Date:

  
April 2016

Project Budget:

 
 $1,396,618

Percent Complete:

 
 70%

Consultant:

  
 Allegheny Construction Co. Inc.